How to complete Manual Activities out of sequence ?
Best Answer
-
Brian_Wiest Customer Super IT Monkey ✭✭✭✭✭If the use case of the SR is one that allows for activities to be completed in any order place them in a Parallel activity. When the workflow reaches a Parallel activity all contained activities become in-process at the same time.7
Answers
It's with these other mechanisms you could make these changes "behind the scenes" so to speak.