You can log time worked on these work items as below.within the Portal by looking under the relevant tabs, see below:
IR - Resolution Tab, then look under the Time Worked heading
SR - Results Tab, then look under the Time Worked heading
CR - Results Tab, then look under the Time Worked heading
James
Correct time is logged on the CR and not the Activities. MA's for example have an Actual Start Date and Actual End Date to log time in but this does not reflect on the CR