Change Requests - If start date changes notify or trigger approvals again
We have some approvals being done and then the implementer changes the start time and I wondered if anyone knows of a way to trigger a notification or to 'reset' the approval process, if the scheduled start/end date is changed? If there is nothing in place it would be good to have the option to introduce something. -
Re: Change Requests - If start date changes notify or trigger approvals again
There are certainly other ways of doing this, but we use a report. For example, I have added "original" start/end and "approved" start/end dates to the CR class, for example. I have an Orchestrator (soon to be converted to SMA) job that updates these fields when changes occur or change manager (only) approval is given, and…